A booth fee is visible before an event. The rest of the day’s costs can hide in travel, parking, packaging, payment charges, preparation and packing down. A useful planning sheet separates these costs without treating every dollar as the same type of expense. This is an educational scenario method, not accounting or tax advice.
Put each cost in one place
Event-fixed costs belong to this particular day regardless of how many units sell: the entered booth fee, parking and other fixed event charges. Per-unit costs change with each sold unit, such as materials, allocated making cost, packaging and an assumed payment cost. If you put an expense in both groups, the tool will count it twice. Write the inclusion rule next to each entry.
A constructed starting scenario
Suppose a maker enters $100 booth fee, $25 travel and parking, and $15 in other event-fixed costs. Total event-fixed cost is $140. Their illustrative product sells for $20, with $7 in entered per-unit costs plus a 3% assumed sales-linked fee. The percentage is an example input, not a current payment-provider rate. The fee is $0.60 per unit, leaving $12.40 in contribution toward event costs.
Make time visible without confusing cash
If the maker spends six total hours preparing, selling and packing down and chooses a $15-per-hour time allowance, the scenario adds $90 to a separate target. The cash-cost coverage threshold and the threshold including that allowance are different. The tool reports both. A chosen allowance does not establish a wage, actual payroll expense or tax deduction.
| Category | In the example | Watch for |
|---|---|---|
| Event-fixed | $140 total | Costs omitted because they were paid earlier |
| Per unit | $7 plus $0.60 assumed fee | Packaging or labor counted twice |
| Optional time target | $90 | Calling a noncash target a cash expense |
Keep the missing-cost list
The planner does not infer taxes, refunds, damaged stock, mixed products or payment-provider rules. If those matter, add a supported allowance where appropriate or use a more detailed model. Use the event-cost worksheet to list what has been included and what remains unresolved before you decide whether a scenario is complete enough to use.